Engineering and shoring plan
Replacement drawings, the temporary support system and the removal sequence, designed by the engineer of record.
Foundation Repair / Replacement
Replacing a foundation under a standing house is one of the most involved projects in residential construction. It is the right answer only when an engineer concludes repair is not — and most cracks never lead there.
Discuss foundation replacementReplacement means removing sections of the existing foundation and building new ones while the house is temporarily supported. It may be partial — one wall line, one corner, the area under an addition — or full, around the entire perimeter and interior supports.
Because the house stays in place, the work is planned around support: how loads are carried while the old foundation is gone, in what order sections are removed and rebuilt, and how the building is set back down and reconnected.
Actual scope and methods depend on the site evaluation and the approved design.
Replacement drawings, the temporary support system and the removal sequence, designed by the engineer of record.
Beams, cribbing and jacks carrying the house while sections of foundation are out. Movement is monitored during the work.
Breaking out old concrete in planned segments, excavating to the design depth and hauling material away.
Locating, protecting or temporarily rerouting gas, water, sewer and electrical lines that run through or near the foundation.
New footings and stem walls with anchorage, followed by setting the house back onto the new foundation.
Repairing affected landscaping, hardscape, siding, plaster, drywall and floors. Some interior cracking can appear as the house is reset.
| Aspect | Contractor evaluation (KB) | Licensed engineer | City or county inspection |
|---|---|---|---|
| Question answered | What is visible and what practical next step fits | What is causing it and what the design should be | Does permitted work match the approved plans |
| When | Before anything is decided | When movement, capacity, soil or design is in question | At permit stages during construction |
| Relied on for | Planning and pricing a defined scope | Professional engineering judgment and drawings | Code compliance of the inspected work |
The structural engineer designs the replacement and shoring and may observe key stages; a geotechnical engineer may be involved when soil drives the design. The building authority reviews the plans and inspects excavations and reinforcement before concrete, and other stages as the permit requires. Utility providers may need to be contacted before excavation. KB coordinates the sequence and reports field conditions to the engineer.
Permits →We read the engineer's report and replacement design and identify access, utilities and sequence questions.
Permit, utility locating, access paths and protection of what stays.
The house is supported; sections are removed, excavated, inspected and rebuilt in the planned order.
The house is set back down and anchored; finishes and site are restored and remaining inspections completed.
No. Concrete cracks for many reasons; most cracks are monitored or repaired. Replacement is an engineering conclusion, not a starting assumption.
Sometimes for parts of the work, but utility interruptions, noise and access limits can make temporary relocation sensible for certain phases. We plan this with you before work starts.
A house cannot be unsupported everywhere. Work proceeds in sections so loads always have a path to the ground.
Exterior areas near the work are disturbed, and some interior cracking can appear when the house is reset. Restoration is part of the scope we define with you.