Permits for a detached ADU

A detached ADU is a new building on your lot. Its permit path is set by state ADU law and each city's local standards, then checked against your specific site: access, utilities, setbacks and any overlays.

01

What decides the path

State framework, local standards

California requires cities to review qualifying ADUs ministerially against objective standards; each city publishes its own local rules. Read the city's current page, not an older summary.

Pre-approved plans are not site approval

Several cities offer pre-approved or standard plans. They simplify the building design; the site is still reviewed.

Utilities decide feasibility

Electrical capacity, sewer route and water service often decide where — and whether — a unit fits.

02

How to prepare this submittal

  1. 1. Confirm the parcel and its overlays

    Zoning, fire, coastal, hillside or historic overlays decide which local standards apply before a footprint is drawn.

    Find the parcel's reviewing authority →
  2. 2. Get a survey and locate utilities

    A detached unit needs a site plan with property lines, structures, trees and the sewer, water and electrical routes to the new building.

    ADU planning guide →
  3. 3. Decide custom or pre-approved plan

    Where a city offers pre-approved or standard plans, choosing one changes the building drawings; the site plan, foundation and utilities stay parcel-specific.

    Compare ADU types →
  4. 4. Ask the provider about service capacity

    Electrical service size, a possible new meter and the sewer connection are confirmed with the provider, often in parallel with plan review.

    See where utilities sit in the sequence →
  5. 5. Submit a complete set

    State law sets a completeness notice and a decision window for ADU applications; both run from a complete submittal, so a missing item restarts the clock.

    What agency fees sit outside a quote →
03

What is specific to this service

The shared stages (authority, planning check, plan check and inspections) are explained once on the permits index; this page records only what differs. See how review usually proceeds

  • Overlays before design

    Coastal, historic or fire-zone status is checked for the parcel first; some cities require a separate approval before the building permit.

  • Foundation and utility inspections

    Inspections typically follow foundation, framing, utilities and final; the city schedules them, not the contractor.

Checklist to bring

  • Property address
  • Site sketch with structures, trees and slopes
  • Electrical panel photo
  • Where the sewer leaves the house, if known
  • Intended use of the unit
04

Questions

Is an ADU permit automatic under state law?
No. State law limits what cities may require, but the application still has to meet objective standards for your site.
Should I use a pre-approved plan?
It can save design effort if it fits your lot. We compare it with site conditions before you commit.