Timeline / Detached ADUs

How a detached ADU is sequenced

A detached ADU adds utility and site steps that a remodel does not have. This page shows the dependency chain from feasibility to final inspection and where schedules usually stretch.

01

What moves the schedule

Feasibility before design

Lot, overlays, access and utility routes are checked first; they decide which design is worth drawing.

Utilities run on their own clock

Utility providers may review service changes separately from the building authority, and their steps can sit on the critical path.

Foundation inspections open the build

Framing does not start until the foundation is inspected, so site and soil surprises affect everything after.

02Dependency map

Illustrative sequence — order and dependencies only, no dates or durations.

Scroll the table sideways on small screens.

Dependency map. Illustrative sequence — order and dependencies only, no dates or durations.
StepWaits forCan run alongsideDecisions, lead times and readiness
Predesign1. Feasibility: zoning, overlays and accessStarts the project—
Owner decision:
Set the size target and confirm detached is the right type.

Choose the ADU type →

Site investigations2. Survey, utility locations and soils1. Feasibility: zoning, overlays and access—

Find the reviewing authority →

Consultant work3. Structural, civil and energy input2. Survey, utility locations and soils—

California Energy Commission — 2025 Building Energy Efficiency Standards ↗

Design development4. Plan choice and construction documents3. Structural, civil and energy input—
Owner decision:
Commit to a custom or pre-approved plan before drawings deepen.

ADU planning guide →

Application acceptance5. Completeness check4. Plan choice and construction documents—
Stated review window:
For an ADU application, Government Code § 66317 requires the agency to say in writing within 15 business days whether the application is complete, listing what is missing.

California Legislature — Government Code § 66317 (ADU application review) ↗

Detached ADU permit notes →

Correction rounds6. Review, corrections and other departments5. Completeness check7. Sewer route, water meter and electrical service requests; 8. Window, door and equipment orders
Stated review window:
The same section requires approval or denial within 60 days of a complete application, unless the applicant asks for a delay. It is a window for one review step, not a duration for your project.

California Legislature — Government Code § 66317 (ADU application review) ↗

How plan review is staged →

Utility readiness7. Sewer route, water meter and electrical service requests4. Plan choice and construction documents6. Review, corrections and other departments; 8. Window, door and equipment orders
Utility:
Confirm whether lines extend from the main house or need a new connection.

Los Angeles Department of Water and Power — Request a meter spot (single-family) ↗

Procurement8. Window, door and equipment orders4. Plan choice and construction documents6. Review, corrections and other departments; 7. Sewer route, water meter and electrical service requests
Long lead:
Windows, exterior doors, electrical gear, heat pumps.
Permit issuance9. Permit issued6. Review, corrections and other departments—
Mobilization10. Access, staging and protecting the main house9. Permit issued—
Occupied house:
The main house usually stays occupied: plan parking, noise, access and short shutdowns.
Construction11. Site work and foundation10. Access, staging and protecting the main house—
Inspections12. Foundation inspection11. Site work and foundation—
Construction13. Framing, systems and finishes12. Foundation inspection; 8. Window, door and equipment orders—
Inspections14. Rough and final inspections13. Framing, systems and finishes; 7. Sewer route, water meter and electrical service requests—
Closeout15. Connections, documents and handover14. Rough and final inspections—

What handover should include →

Your progress notes

Tick a step when you consider it done. A tick is your own note, not evidence that an authority approved anything. Nothing is saved or sent.

Can start now, by your notes: 1. Feasibility: zoning, overlays and access

Distinctions that matter

  • Construction duration vs end-to-end

    Construction time counts days trades are on site. End-to-end time adds design, engineering, review, corrections, procurement and close-out. Ask which one any schedule describes.

  • Agency metric vs your project

    When an authority publishes review statistics, they describe past applications in aggregate. They are not a prediction for one parcel's drawings and corrections.

  • Why this page gives no durations

    We found no published basis that would make a single number honest for every house, so the sequence and its dependencies are shown instead. Your schedule is set once drawings and review requirements are known.

Illustrative example — not a client

On one lot the sewer line can extend from the main house; on another a new connection is needed. Both buildings take the same construction effort, but the second schedule waits on the provider's steps before final.

What each phase means: phase glossary

03

Questions

Does choosing a pre-approved plan settle my ADU schedule?
No. It may reduce design and some review work where the authority offers that path, but the site plan, foundation, access and utility connections still need project-specific answers. Track each unresolved dependency and who must answer it before scheduling the next stage. A permit-review window is not the time from your first design conversation to move-in.
Is there a state review deadline?
For ADU applications, Government Code § 66317 sets a 15-business-day completeness notice and a 60-day decision window on a complete application (see the dependency map). These cover review steps only; correction rounds, other agencies, utilities and construction sit outside them.