Timeline / Garage conversions
How a garage conversion is sequenced
A garage conversion starts with what already exists: its records and condition decide how much of the chain is needed. This page shows the sequence and the points that most often move it.
What moves the schedule
Records before drawings
Confirm how the garage was permitted. Missing records can add a step to document or correct the existing structure.
Assessment decides keep or replace
Slab, framing and roof are assessed against living-space requirements; that answer sets the construction sequence.
Smaller scope, same inspections
Even with less new structure, rough and final inspections still apply to the work performed.
02Dependency map
Illustrative sequence — order and dependencies only, no dates or durations.
Scroll the table sideways on small screens.
| Step | Waits for | Can run alongside | Decisions, lead times and readiness |
|---|---|---|---|
| Predesign1. Existing garage: records, slab and height | Starts the project | — |
|
| Site investigations2. Structure check and utility locations | 1. Existing garage: records, slab and height | — | |
| Design development3. Layout, egress, insulation and energy | 2. Structure check and utility locations | — |
California Energy Commission — 2025 Building Energy Efficiency Standards ↗ |
| Application acceptance4. Completeness check | 3. Layout, egress, insulation and energy | — |
California Legislature — Government Code § 66317 (ADU application review) ↗ |
| Correction rounds5. Review and corrections | 4. Completeness check | 6. Electrical load and plumbing tie-ins; 7. Windows, door and mini-split orders |
California Legislature — Government Code § 66317 (ADU application review) ↗ |
| Utility readiness6. Electrical load and plumbing tie-ins | 3. Layout, egress, insulation and energy | 5. Review and corrections; 7. Windows, door and mini-split orders |
|
| Procurement7. Windows, door and mini-split orders | 3. Layout, egress, insulation and energy | 5. Review and corrections; 6. Electrical load and plumbing tie-ins |
|
| Permit issuance8. Permit issued | 5. Review and corrections | — | |
| Mobilization9. Empty the garage; protect driveway and house | 8. Permit issued | — |
|
| Construction10. Door infill, slab work, framing, systems, finishes | 9. Empty the garage; protect driveway and house; 7. Windows, door and mini-split orders | — | |
| Inspections11. Rough and final inspections | 10. Door infill, slab work, framing, systems, finishes; 6. Electrical load and plumbing tie-ins | — | |
| Closeout12. Documents and handover | 11. Rough and final inspections | — |
Your progress notes
Tick a step when you consider it done. A tick is your own note, not evidence that an authority approved anything. Nothing is saved or sent.
Can start now, by your notes: 1. Existing garage: records, slab and height
Distinctions that matter
Construction duration vs end-to-end
Construction time counts days trades are on site. End-to-end time adds design, engineering, review, corrections, procurement and close-out. Ask which one any schedule describes.
Agency metric vs your project
When an authority publishes review statistics, they describe past applications in aggregate. They are not a prediction for one parcel's drawings and corrections.
Why this page gives no durations
We found no published basis that would make a single number honest for every house, so the sequence and its dependencies are shown instead. Your schedule is set once drawings and review requirements are known.
Illustrative example — not a client
Two similar garages: one has its original permit on file, the other was enlarged without one. The second adds a documentation step before design can be finalised.
What each phase means: phase glossary
Questions
- Is a conversion quicker than building new?
- It often has less new structure, but records and the existing condition can add steps. Compare both sequences for your lot.
- Where do I find the garage's permit history?
- From the authority that reviews your address; the permit pages list each authority's starting points.
Service, permits and timing
This service by community
- ADU construction in Los Angeles
- ADU construction in Beverly Hills
- ADU construction in Santa Monica
- ADU construction in West Hollywood
- ADU construction in Culver City
- ADU construction in Venice
- ADU construction in Calabasas
- ADU construction in Burbank
- ADU construction in Glendale
- ADU construction in Pasadena
- ADU construction in Malibu
- ADU construction in Inglewood