Grading, drainage and foundation planning before layout and pricing

Earthwork, site water and foundations are three views of one problem: how the house meets the ground. Each finding on the site raises a question for a specific professional, may change a specific document or scope, and should be decided before anyone prices the work. This guide organizes those handoffs. It contains no engineering values or design solutions.

Written · KB Remodeling

The short answer

Treat grading, drainage and foundations as one coordination sequence: survey and geotechnical findings come first, the civil and structural engineers turn them into grading, drainage and foundation design, and the building authority reviews what its rules require. In the City of Los Angeles, LADBS says a soils and/or geology report is usually required for its Grading Division's technical review before grading permits issue.

Who this applies to

Owners planning a new or replacement house, a large addition or an ADU where earthwork, site water or foundation choices may matter. Whether a parcel needs a grading permit, retaining walls, stormwater measures or a particular foundation depends on the authority's rules and the engineers' design for that parcel, not on a hillside label.

01 · When it applies

One sequence, three questions

Who reviews site work depends on where the parcel is: a City department within an incorporated city, or LA County Public Works for unincorporated County land, which lists retaining walls among its trade permit types. In the City of Los Angeles, LADBS's Grading Division reviews soils and geology reports and inspects grading work.

The owner's job is not to choose a foundation or a drainage method. It is to make sure the right evidence exists, that each question has a named professional, and that the answers reach the drawings and the estimate in the same revision.

Ask yourself

  • Which authority reviews grading, drainage and foundation drawings for this parcel?
  • Which professional on the team owns each of the three questions?

02 · The decision

Grading, earthwork and access

Grading questions start with the topographic survey and the planned floor levels: how much the ground changes, where excavated material goes, how equipment reaches the work and whether walls hold back soil. LADBS describes grading permits as required for grading work in its designated hillside grading area and in other defined circumstances; read the authority's current criteria for your parcel rather than assuming either way.

Access shapes earthwork as much as volume does. A narrow street, a shared driveway or a steep approach can limit equipment and hauling, and may raise questions about haul routes or staging that the authority or neighbors care about.

Grading matrix: finding → question → affected scope → decision before pricing
Site findingQuestion forPossible affected document or scopeDecision before pricing
Planned floor well above or below existing gradeArchitect and civil engineerGrading plan; retaining walls; stairs and drivewaySet floor levels and accept the earthwork they imply
Excavated material must leave the siteCivil engineer; authorityExport quantities; haul route conditionsConfirm whether haul-route review applies
Limited equipment accessContractor; civil engineerStaging, equipment and sequenceAgree access assumptions to price against
Walls retaining soil near property linesStructural and geotechnical engineersWall design; permits; neighbor coordinationConfirm wall scope is in the drawings, not an allowance guess

Source for this section

03 · The decision

Drainage, stormwater and site water

Water moves across and through a site before and after construction. The questions are where it comes from, where it goes today, how the new house and paving change that, and what the authority requires. The City of Los Angeles expanded its stormwater mitigation requirements with a Low Impact Development ordinance applied to projects requiring building permits, and LA Sanitation publishes an LID handbook; whether and how those requirements apply to your project is for the civil engineer and the City to confirm.

Keep drainage decisions in the layout phase. Moving the house, the driveway or a patio after drainage is designed can change the design, and drainage elements may need space, access or easements.

Drainage matrix
Site findingQuestion forPossible affected document or scopeDecision before pricing
Water flows onto the lot from uphill or a neighborCivil engineerGrading and drainage planAgree how existing flow is to be handled in the design
New roof and paving add hard surfaceCivil engineer; authorityStormwater measures on the site planConfirm which local requirements apply
No obvious place for water to goCivil engineer; public worksDrainage route; easement or connection questionsResolve the outlet question before final layout
Groundwater or seepage noted in the geotechnical reportGeotechnical and structural engineersFoundation and below-grade waterproofing scopeCarry the finding into foundation decisions

04 · The decision

Foundations as an interface

A foundation is where site evidence, structural design and construction scope meet. The geotechnical report supplies findings and recommendations; the structural engineer designs the foundation using them and the house's loads; the contractor prices and builds what the drawings show, often with the geotechnical engineer observing parts of the work. A neighbor's foundation type is not evidence for yours.

For the owner, the useful questions are whether the drawings and the geotechnical recommendations are the same revision, which items are left for field decision, and who observes them.

Foundation interface matrix
Site findingQuestion forPossible affected document or scopeDecision before pricing
Geotechnical recommendations depend on the final footprintGeotechnical engineerReport addendumFreeze the footprint, then confirm the report covers it
Structural drawings issued before the latest reportStructural engineerFoundation drawingsReconcile both to one revision
Construction observation items listedGeotechnical engineer; contractorInspection and observation scheduleInclude observation in budget and schedule
Existing foundation to be reused or removedStructural engineer; contractorDemolition, repair or new foundation scopeDecide reuse or replacement before bids

05 · An example

Fictitious scenario: a sloping replacement lot

A generalized, fictitious owner replaces a house on a sloping lot. The survey shows the street lower than the rear yard, the geotechnical report notes seepage, and the architect wants a lower-level garage. The three matrices turn that into decisions: floor levels and export questions for grading, an outlet question for drainage, and a foundation and waterproofing scope tied to the report. Bidders receive one drawing revision with those items shown, and site work is priced as separate lines rather than a single allowance. No cost or duration is assumed here.

Ask yourself

  • Which site decisions are still open in the drawings you plan to price?

Who resolves which question

QuestionResolved byMay be reviewed by
Existing ground and boundariesLand surveyorBuilding authority (as part of plans)
Subsurface conditionsGeotechnical engineer / engineering geologistBuilding authority's grading or geotechnical review
Grading and drainage designCivil engineerBuilding authority; public works
Foundation and retaining-wall designStructural engineer, using geotechnical recommendationsBuilding authority
Pricing and sequenceContractor, from the issued drawingsOwner

A scenario to consider

Fictitious, generalized scenario: two bids differ widely because one assumed retaining walls and the other did not. The owner asks the engineers to show the wall scope in the drawings and rebids both on the same revision.

Planning scenario

Bring this to your conversation

  • Confirm the authority that reviews grading, drainage and foundations
  • Get the survey and geotechnical report before fixing floor levels
  • Assign grading, drainage and foundation questions to named engineers
  • Resolve the drainage outlet before final layout
  • Reconcile foundation drawings and geotechnical report to one revision
  • Price site work as separate lines from the issued drawings

One more question

Does a hillside lot always need a grading permit or a special foundation?

Not necessarily. That depends on the authority's rules for the parcel and on the engineers' design. A hillside label is a reason to ask, not an answer.

Official references

For requirements specific to your property, consult the local reviewing authority.

About this guide

Published by KB Remodeling from the official sources cited. It is not attributed to an individual author and does not claim review by an architect, engineer or attorney. We receive remodel, ADU, new-home and rebuild inquiries; scope, licensing and location are reviewed before any next step.

Your next step

Discuss scope and location

KB Remodeling · Greater Los Angeles

Have a home in mind?

Tell us about the house, the goal and the timing. Let's start the conversation.

Start the conversation