Field notes / Homeowner guide
The phases of building a new home, and what moves the schedule
A new-home schedule is a chain of phases with different owners: design, approvals, procurement, construction and handover. Knowing what drives each phase helps you plan without relying on a fixed completion date.
Written · Revised · KB Remodeling
The short answer
Plan a new home as a chain of phases, each waiting on a decision, a report, an agency or a utility. Ask for a sequence that shows which phases depend on each other and which can overlap, with assumptions written down — not a completion date.
Who this applies to
For owners planning a ground-up house on a lot. Remodels, detached ADUs and garage conversions follow different sequences, explained on the timeline pages.
01 · When it applies
Phases, owners and true dependencies
A new home moves through predesign, site investigations, consultant work, design development, application acceptance, correction rounds, permit issuance, procurement, mobilization, construction, inspections, utility readiness and closeout. Each has a different owner: you, the design team, an agency, a utility or the builder.
Some phases can overlap — selections and utility applications can proceed while corrections are answered. Others are real dependencies: construction documents wait on site data, and work on the permitted scope waits on issuance. Planning well means knowing which is which, not compressing every phase.
Ask yourself
- Which phases depend on your decisions?
- Which can overlap without risk of redesign?
02 · The decision
Site information before design commits
Survey, soils and utility availability decide what can be designed. When a report arrives after the layout is fixed, engineering and drawings can be redone. Ordering site investigations first rarely feels like progress, but it protects the design phase from rework.
Ask the design lead which consultant inputs each drawing set depends on, and who commissions each report.
Ask yourself
- Which reports exist already, and which must be ordered?
- Which drawing waits on each report?
03 · Comparing the options
Owner decision deadlines
Owner decisions have deadlines set by what depends on them, not by the calendar. A late layout change reopens consultant work; a late window choice can push procurement past the start of framing.
Keep a list of decisions with the phase each one gates, and record changes in writing once drawings are submitted.
- Massing and layout
- Decided before construction documents; later changes reach structure, energy and site plans.
- Window and door package
- Decided during design development; affects energy compliance and is often a long-lead order.
- Finish selections
- Can be carried as allowances, but should be final before procurement to avoid waiting on deliveries.
Ask yourself
- Which decision is the next gate?
- How will a change after submittal be approved?
04 · The decision
Acceptance, corrections and issuance
Where planning review applies, it usually comes before building plan check. An agency first confirms the application is complete enough to review; acceptance is not approval. Reviewers then issue comments, and the number of correction rounds is not known in advance.
If an agency publishes processing statistics, read the period and the application class they describe. They summarize past applications and are not a guarantee for one parcel. Permit issuance follows approved plans, paid fees and any clearances from other departments.
Ask yourself
- Which reviews does this parcel trigger?
- Who answers corrections, and how quickly?
Source for this section
05 · The decision
Procurement and utility readiness
Long-lead items — windows, structural steel, electrical gear, mechanical equipment — can be ordered once design is fixed, often while corrections are still being answered. Utility providers review service requests on their own process, separate from the building authority.
Temporary power and water are utility requests too, and final sign-off can wait on a service connection even after construction looks finished.
Ask yourself
- Which items have the longest lead times?
- Has each utility confirmed capacity and meter locations?
06 · Next step
Construction, inspections and closeout
Construction moves through grading, foundation, framing, envelope, systems and finishes, paced by staged inspections and deliveries. A failed inspection is corrected and reinspected before work is covered.
Closeout includes final inspection, energized service, a punch list and documents. Plan a move-in after these steps rather than at the end of construction activity.
Ask yourself
- What documents will you receive?
- Who schedules final inspections?
Source for this section
Loading Illustrative dependency sequence…
A scenario to consider
Illustrative scenario, not a client project: an owner whose lot needs a soils report learns that ordering it first keeps the engineering from waiting later in design.
Planning scenario
Part of the custom-home planning series: Custom home planning
Bring this to your conversation
- List owner decisions by design stage
- Ask which reviews the parcel triggers
- Identify long-lead products early
- Agree how changes are approved
- Plan move-in after final sign-off
Terms used here
- Planning review
- Review of applicable land-use and site rules, distinct from checking construction drawings for building safety.
- Plan check
- Agency examination of submitted construction documents; the reviewer may request corrections before approval.
- Clearance
- A required sign-off or referral from another agency or discipline when applicable to the project.
One more question
How long does it take to build a custom home?
It varies by design decisions, the reviews the parcel triggers, correction rounds, product lead times and construction conditions. Ask for a phase-by-phase schedule with its assumptions.
Official references
Research the property · Web resource · English source
Los Angeles City Planning — Zoning search (ZIMAS)Use this for: Look up City of Los Angeles parcel and zoning information before asking Planning what applies.
Prepare plans and ADUs · Web resource · English source
California Energy Commission — 2025 Building Energy Efficiency StandardsUse this for: Find the 2025 energy standards and discuss the applicable compliance path with the design team.
Prepare plans and ADUs · PDF · English source
California Building Standards Commission — Information Bulletin 25-01 (July 1, 2025)Use this for: Discuss the code-cycle bulletin and application timing with the reviewing office.
Request utility service · Web resource · English source
Los Angeles Department of Water and Power — Request a meter spot (single-family)Use this for: Ask LADWP about the meter-location request for the proposed single-family or ADU scope.
For requirements specific to your property, consult the local reviewing authority.
About this guide
Published by KB Remodeling from the official sources cited. It is not attributed to an individual author and does not claim review by an architect, engineer or attorney. We receive remodel, ADU, new-home and rebuild inquiries; scope, licensing and location are reviewed before any next step.